M-Communications was appointed as sole-contractor by third party operator - Crown Castle to install a Neutral Host iDAS to ensure visitors are seamlessly connected as they explore exhibitions.
Scope of Work
Supporting the iDAS installation included IDF location build outs which consisted of all civil and electrical work; installation of Crown-provided equipment; all cable ladder (CCI and futures) and BTS racks for CCI and cabling of the associated DAS equipment and Volt-server components.
High-level project details :
Remote Locations: SOLiD Remotes supporting 700/ 850/ 1900/ 2100 and 2.5 HDD MHz remotes and fire retardant backboards, Install all remotes, antennas, associated power/ fiber/ grounding, fiber back to the hub
Power Equipment for remote equipment: Voltserver Rectifiers and wiring to SOLiD remotes
Antenna locations : 30 Laird Omni directional antenna (model CFD69383P30D43F) and fiber distribution, Installation of 1 x 144 port and 1 x 24 port fiber distribution panel in the initial remote location and 1 x 24 port fiber panel in each of the remaining three remote locations.
Installation of all coax and passive components along with all associated connectors, per iBwave design and RF BOM
Commissioning and testing : Fiber – 1310 & 1550 Insertion Loss and Bidirectional OTDR testing for all fiber strands; Coax – Complete sweep tests for all coax runs in both low and high band frequencies; Coax – PIM tests for all coax runs in both low and high band frequencies. Must meet -153dbc standards
Our problem-solving skills were put to the test at the Perez Museum which has solid concrete walls and ceilings that challenged us with routing for cables. Substantial concrete coring and X-Rays were required. Our knowledge and extensive project management skills were required to meet the tight-deadlines that made this job a success and delighted our client.